NEW QUESTION 37
You want to perform capacity availability checks on your production orders. What must be set for this to occur? Note: There are 2 correct answers to this question.

  • A. Checking rule and group must be assigned.
  • B. PRT Availability check must be set.
  • C. Indicator Relevant for finite scheduling must be set.
  • D. Checking control must have an overall profile assigned in customizing.

Answer: C,D

 

NEW QUESTION 38
What are some of the SAP Fiori user types?
There are 3 correct answers to this question.
Response:

  • A. Developer
  • B. Business partner
  • C. Employee
  • D. Occasional
  • E. Expert

Answer: A,D,E

 

NEW QUESTION 39
How can SAP S/4HANA support a GMP compliant production process? Note: There are 3 correct answers to this question.

  • A. Predefined GMP compliant process order types to meet audit requirements
  • B. Documentation of quality data with Quality Management
  • C. Recipe approval (with Engineering Change Management)
  • D. Use of the GMP compliant flag in relevant master data applications
  • E. Use of the digital signature function to check and run business processes

Answer: B,C,E

 

NEW QUESTION 40
The procurement type of your material is set to "E" for In-house production. Which of the following is valid to determine a source of supply in SAP S/4HANA?
Please choose the correct answer.
Response:

  • A. Production Version
  • B. Purchasing Info Record
  • C. Selection Method
  • D. Contract

Answer: A

 

NEW QUESTION 41
You use planning strategy Finite Scheduling - with Reverse and want to allow scheduling in the past. How can you achieve this?

  • A. Specify a negative planning horizon in the strategy profile.
  • B. Specify a positive planning horizon in the strategy profile.
  • C. Specify a positive offset time in the strategy profile.
  • D. Specify a negative offset time in the strategy profile.

Answer: D

 

NEW QUESTION 42
How does the new Inventory Management Data model contribute to the reduction of the data footprint?
There are 3 correct answers to this question.
Response:

  • A. By eliminating inventory history tables
  • B. By eliminating fields for different stock types
  • C. By eliminating material master tables
  • D. By eliminating inventory tables
  • E. By eliminating hybrid tables

Answer: A,B,D

 

NEW QUESTION 43
How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.

  • A. Reduce the planning window.
  • B. Form optimum sequences to reduce setup times.
  • C. Select an alternative mode on a resource.
  • D. Execute a new production planning run.
  • E. Adjust the available capacity.

Answer: B,C,E

 

NEW QUESTION 44
You are using heuristic SAP_ERP_001. Which of the following criteria are included in the automatic source determination logic when a planned order is created?
Please choose the correct answer.
Response:

  • A. Delivery date
  • B. Costs
  • C. Quota arrangement
  • D. Component availability
  • E. Vendor rating

Answer: C

 

NEW QUESTION 45
Which of the following processes lead to an entry in the MRP planning file? Note: There are 3 correct answers to this question.

  • A. Creation of dependent requirements
  • B. Change of the storage bin
  • C. Creation of a sales order
  • D. Change of the material's procurement type
  • E. Creation of a purchasing contract

Answer: A,C,D

 

NEW QUESTION 46
Before a user can add multiple production versions in a material master, what information should be collected?
There are 3 correct answers to this question.
Response:

  • A. Validity dates
  • B. Task list group number
  • C. BOM status
  • D. Lot sizes
  • E. Work center hierarchy

Answer: A,C,D

 

NEW QUESTION 47
Which advanced functionality has been embedded in SAP S/4HANA?
There are 3 correct answers to this question.
Response:

  • A. Backorder processing
  • B. Supply Network Planning
  • C. Capacity planning
  • D. Demand planning
  • E. Available-to-promise

Answer: A,C,E

 

NEW QUESTION 48
In your project, you have several materials that are planned by different people. How can you assign the planning responsibility?

  • A. MRP controller
  • B. MRP planning file
  • C. MRP type
  • D. MRP group

Answer: A

 

NEW QUESTION 49
What do you use to schedule operations from planned orders so that the production plan can be fulfilled?

  • A. Demand Planning (DP)
  • B. Supply Network Planning (SNP)
  • C. Capacity Requirements Planning (CRP)
  • D. Material Requirements Planning (MRP)

Answer: D

 

NEW QUESTION 50
What are main innovations in manufacturing in SAP S/4HANA?
There are 3 correct answers to this question.
Response:

  • A. Monitor Production Orders Fiori app
  • B. Material Coverage Fiori app
  • C. Flow manufacturing
  • D. Lock-free inventory movements
  • E. Rough-cut capacity planning

Answer: A,B,D

 

NEW QUESTION 51
How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question.

  • A. By plant
  • B. By material type
  • C. By industry
  • D. By period

Answer: A,D

 

NEW QUESTION 52
Which functional capabilities does the Detailed Scheduling Board have?
There are 2 correct answers to this question.
Response:

  • A. Change sales order quantities
  • B. Undo for drag & Drop planning activities
  • C. Enter time-ticket confirmation for production orders
  • D. Change planned order quantities

Answer: B,D

 